HOME  |   RESEARCH  |   CAREERS  |   CAMPUS  |   PHONE  |   CONTACT

Timeline:

 
Brief History
Timeline
Questions & Answers
Recent Images
Why Dismantlement?
     Why Now?
Weekly Update
Dismantlement Phases

Building 470
1953 Construction was completed on Building 470, a pilot plant for production of microorganisms thought to have use as weapons.

1954-65
Small-scale pilot-plant production and laboratory-scale research of microorganisms, most notably, Bacillus anthracis, etiologic agent of anthrax.

1965-69
Continued laboratory-scale research.

1969
U.S. renunciation of biological weapons, cessation of the U.S. program, and destruction of stockpiles. Building 470 became a storage facility.

1970-71
Decontamination and decommissioning of the building. Over 1300 samples were taken in the building to verify successful decontamination.

1971
Building 470 and Fort Detrick buildings declared safe for occupancy by those not immunized against anthrax. Surrounding buildings were deeded to the National Institutes of Health and retrofitted for cancer and infectious disease research.

1988
Department of Defense transferred ownership of Building 470 to the National Cancer Institute. The building, used only as a storage facility for almost 18 years, was in a state of structural deterioration, according to civil engineers at Ft. Detrick.

1997
A report determined that the reuse or renovation of Building was impractical and recommended demolition as the “fiscally prudent alternative.”

2000
In March, operations contract staff at Ft. Detrick issued a report on the structural integrity of Building 470. The report, based on a thorough inspection of the facility, identified numerous safety and structural deficiencies. These included a severely damaged roof; water intrusion into structural steel; buckling and outward deflection of exterior mortar and brick veneer; corroded beams, columns, and lintels; and cracked and peeling plaster and paint.

2000
In April the National Institutes of Health approved the concept of demolition. A panel of three independent biological safety experts reviewed the existing data on sampling and testing, and determined that construction and demolition workers did not need to be immunized against anthrax to dismantle the building. The experts’ report did note presence of pigeon guano and potential health risk resulting from it.

2001
National Environmental Policy Act and Historic Preservation Act documentation were completed in anticipation of dismantling and demolition. Professional engineers conducted a search for an appropriate firm to perform the demolition, including mitigation of any residual hazards, especially lead or asbestos.

2002
In October, Southern Research Institute took an additional 790 samples in the building to verify decontamination. The samples were tested for presence of B. anthracis using standard culture methods and more sensitive methods using DNA; all samples were negative for any trace of the bacterium that causes anthrax.

November 2002 to Present
Some 20 information sessions, detailing the history, decontamination and dismantling plans have been presented for NCI-Frederick and Fort Detrick employees.

February 2003
Articles and stories in newspapers and the electronic media on the planned dismantlement of Building 470
The Path Ahead:

Winter 2003
: Asbestos removal

Spring 2003
: Phase 2 dismantlement: removal of equipment and non-loadbearing walls

Summer or Autumn 2003
: Phase 3 dismantlement: removal of building shell

  National Cancer Institute (NCI)      National Institutes of Health (NIH)      Department of Health and Human Services (HHS)      FirstGov.gov